CHAPTER IX. DECAY AND PAINTING.

Previous

The author has collected particulars as to the amount and rate of rusting in metallic structures which are of some interest. In all such instances it is very necessary to note the conditions which have obtained during the process of wasting, as without this, misleading conclusions may be drawn. The information given relates in all cases to wrought iron, unless otherwise stated.

A plate-girder bridge, having girders under rails, was found to be badly rusted. The atmospheric conditions were unusually trying, the air being damp and impregnated with acid fumes from adjacent steel works. That the wasting was largely due to this latter cause was indicated by the fact that the girders nearest to the steel works suffered more than those farther removed and partly sheltered from the corrosive influence.

The webs were in places eaten right through, having lost a mean amount of about 1/8 inch full on each surface in twenty-eight years. Painting had not been well attended to.

In a similar bridge, not a great distance from this, but sufficiently far away to modify the conditions for the better, considerable wasting was also observed, but more particularly where the girders had been built into masonry, which, loosening with the constant movement of the girder-ends, had allowed moisture to collect, and rust to develop, without the chance of repainting these surfaces. The amount of waste at the places indicated was, as in the last case, about 1/8 inch on each face, and in the same time, other parts of the girders having suffered less.

Fig. 58.

A third plate-girder bridge, with outer main girders, cross-girders, and plated floor, carrying a road over a railway and sidings, and which was known to have been neglected in the matter of painting, was very badly rusted, both as to the cross-girders and floor-plates. The atmosphere was somewhat damp; the chief cause of deterioration was, however, the smoke and steam from locomotives, which frequently stood for some time, during shunting operations, directly under the bridge. The webs of the cross-girders, which were originally 1/4 inch thick, had rusted into occasional holes during fourteen years—i.e. 1/8 inch from each surface in that time. When removed a little later the wasting was so complete that it was possible to knock out with a light hammer the remains of the web between flanges and stiffeners, so as to leave an open frame only. One of the cross-girders was so treated by the men engaged upon the work, when it presented the appearance shown in Fig. 58.

In another case—that of a bridge with lattice girders under rails—the ends were built into masonry, which had, of course, loosened, with the usual result. The air of the locality was certainly pure, but somewhat damp. The general condition of the ironwork was good, but end-bars of the diagonal bracing, where they had been closed in, had lost 1/8 inch on each surface in thirty-three years. The top flanges immediately under the timber floor were in a very fair state, which is of some interest when it is considered that these were made of steel of the same kind as that already noticed as being used in the construction of small girders (see Fig. 46, ante), described in the chapter upon “High Stress,” both cases dating from the year 1861. The painting upon the lattice-girder bridge had been pretty well attended to; but in the case of the small steel girders it had been greatly—perhaps altogether—neglected; this, coupled with adverse atmospheric conditions, had produced the result that the rate of rusting had for the small girders been much greater than that of the steel top flange referred to, being fully 1/8 inch on each surface, as against a negligible amount under the more favourable circumstances.

Girder-work over sea-water, as in piers, seems to rust at a sensibly greater rate than inland work under average conditions; but it is hardly practicable to make any strict comparison, as in either case the rate of oxidation is so much affected—even controlled—by the care bestowed upon the structures. This general conclusion is based upon the results of examination of wrought-iron girder-work over sea-water of ages varying from fourteen to forty-four years. It should be remarked, however, that in one case steel girders but five years old, and which were frequently wetted with sea-spray, were found to be wasting rather badly—the paint refusing to keep upon the surface.

It may be concluded from the above instances, and from others which have come under notice, that wrought-iron work, if not properly cared for in respect to painting, or under conditions otherwise bad, may be expected to rust at a rate which corresponds to the loss of 1/8 inch on each surface in from fifteen to thirty years; but with proper care as to painting, and exclusive of exceptionally bad conditions, it does not appear to waste at any measurable rate. In some instances, upon scraping the paint from girders which had been in use for thirty years, the author has found, beneath the original red lead, the metallic surface bright and clean, showing no trace of rust.

Of ordinary steelwork the same cannot be said, the common experience being that mild steel is very liable to be attacked by rust. With passable care in the bridge-yard during manufacture, such that with wrought iron no after-trouble would be noticeable, steel is very liable to show, within a year of being built up, numerous little blisters on the painted surface; any one of these being broken away discloses a small rust-pit. This is more often seen on the flange surfaces (horizontal) than on web surfaces (vertical), but it is probable the position has little to do with the matter, and that it is rather due to the fact that rust has been earlier started on the flange-plates, upon being put through the drilling-machines and inundated with slurry, which occurs only to a more limited extent with webs having fewer holes. The heads of steel rivets do not show this tendency to “pit,” or to early development of rust. The riveting is about the last operation in making a girder, each rivet being freed of all rust by heating, and quickly coming under the protection of oil or paint. It may happen in this way that the heads of rivets on a girder may be exposed without protection for as many hours only as the rest of the work for weeks, which fully accounts for the difference in behaviour.

The essential point to be observed in all steelwork is to prevent, if possible, the first development of rust, for once begun it is much more difficult to arrest than in iron; for this reason, oiling of all material for a steel bridge, at a very early stage of its existence, cannot be too strongly insisted upon. This practice, however, makes the work so objectionable, and even dangerous when being lifted—because of the liability to slip—to the men engaged upon it, that it is commonly very difficult to ensure it being done sufficiently soon to satisfy a careful inspector. If the work is carried out under cover, the requirement is less urgent. Strictly, all material should be oiled so soon as rolled, but the author does not remember to have seen this done at any of the mills he has visited, though it is common enough to find it specified.

Ironwork does not need the extreme care which should be bestowed upon steelwork, but it is desirable that it should be painted as soon as possible, the surfaces being first thoroughly cleaned.

There is, probably, for painting girder work nothing to beat good red lead as a protective coating; but there is considerable difficulty in getting it reasonably pure, without which quality its utility will be greatly reduced. The question of purity will, however, be found to be largely a question of price. It may be stated broadly that, whether for steel or for iron, the first protective covering is, perhaps, the most important of any it will ever receive.

In repainting old work, care should be taken to remove all traces of rust previous to laying on the new coat. It is not an altogether uncommon practice to repaint old structures by dealing only with the parts readily accessible, which, being less liable to rust, probably but little need it; leaving those parts which are difficult of access, and where rust is developing, untouched; treating the whole business as a matter of appearance simply. This, it need hardly be said, is indefensible. It is better rather to neglect the surfaces freely exposed and ventilated, and devote the whole care upon those other parts, confined and difficult to get at; taking the trouble necessary to remove ballast, timber, or whatever may obstruct the operation, in order that the bad places may be thoroughly scraped, and then painted. Those parts which most need attention may cost, perhaps, to reach—and deal with when exposed—ten times as much per yard of surface as the rest of the superfices, which needs little, and is always accessible; but the cost should not deter the proper carrying out of the work, as it will prove the very worst sort of economy to deal with painting in a perfunctory manner.

It should be noted that girder work, whether of wrought or cast iron, when embedded in lime or cement concrete, or mortar, generally proves to be very well preserved, provided that close contact has obtained. Cast-iron girders, when carrying jack arches resting upon the bottom flanges, are found after long use to be in remarkably good order, when finally taken out, having, indeed, the surface appearance of new girders. Much the same remarks apply to girders of wrought iron carrying jack arches, where protected by the brickwork; provided that the girders are sufficiently stiff to minimise deflection, and allow the masonry or brickwork to adhere to the surfaces.

Such girders are in a very different condition to those previously referred to, in which the ends of the girders, carrying a light floor structure, are built into masonry where the deflection slope is greatest; though, apart from the few cases where adherence can be relied upon, building-in is an undesirable practice, and has the disadvantage that after-examination is only possible by removing portions of the masonry, which it is evident would very seldom be resorted to.

Cast iron has ordinarily—unlike wrought iron or steel—great capacity for resisting rust, and will, after many years of absolute neglect, appear but little the worse; an advantage which is the more pronounced when considered relatively to the greater thickness of the thinnest parts in cast-iron girders, the percentage of waste being proportionately lessened.

Cast iron does, however, behave somewhat badly in sea-water, the metal sometimes losing its original character, and becoming in time quite soft; though, if not worn away, as by the attrition of shingle, maintaining its original bulk.

Of some forty-five cast-iron piles belonging to various structures, examined whilst engaged upon sea-pier work for Mr. St. George-Moore, though the author found somewhat diverse results, in no case did there appear to be any general softening of the whole thickness, but a distinct change for some definite distance inwards, generally to be decided without difficulty, beyond which the metal appeared to retain its original character. In all cases any material depth of softening was found close to the ground, this depth rapidly decreasing higher up, till, at a height of 5 feet, but little if any softening could be detected. At 2 feet above ground the softening was frequently but one-quarter of that at ground level. There was, too, often a considerable difference in the behaviour of different piles in the same structure under similar conditions; one pile being found to have only one-fourth part of the softening noticed in others, or possibly none at all. For six different structures the amount of softening near ground level, of about twenty-five piles examined, was as given in the table on the next page.

The greatest depth of softening found (see No. 2) was 9/16 inch, 1 foot above ground, in a pile thirty-six years old. The decayed material when removed was of a soft, greasy consistency, perfectly black, which a few hours later was found to have changed to a dry yellow powder, by the rapid absorption, it may be supposed, of atmospheric oxygen. It is apparent, therefore, from this example that deterioration may proceed to a considerable depth; but it should be observed that other piles of the set showed softening at ground level of 1/8 inch only.

Softening of Cast-Iron Piles in Sea-Water.

No. Age. Maximum
Softening.
Maximum
Rate of
Softening.
Mean Rate
of
Softening.
Quality
of
Metal.
Materials Entered
by Piles.
1 17 years 5/16 in. 1/8 in. in 7 years 1/8 in. in 15 years Soft Extremely soft sandstone.
2 36 9/16 1/8 in 8 1/2 No result Rubble mound.
3 32 3/8 1/8 in 11 1/8 in. in 15 years Moderately hard Fine sand.
4 38 1/10 1/8 in 47 1/8 in 140 Hard Extremely hard rock.
5 17 Small Negligible (?) Sand and Shingle.
6 14 Negligible Ditto (?) Sand.

The least rate of softening noticed, apart from those structures of a more recent date, in two of which it was very slight, occurred in a pier thirty-eight years old (No. 4), where, of three piles tested, two were quite hard, and the third softened 1/10 inch only.

Whatever may be the precise cause of the change, it does not appear to be affected by the period or percentage of immersion during the rise and fall of tides.

Fig. 59.

This will be clear from the diagram, Fig. 59, which refers to four piles (No. 3 of table), all of the same age, in the same structure. On each pile the depth of softening is given at points in strict relation to each other, and to the tidal range. The percentages of immersion for the various heights are also given, from a study of which it will be apparent that these have no relation to the amount of softening; this, indeed, is always greatest near the ground, at whatever actual height it may be. For instance, pile A was at ground-level softened 1/4 inch, that point being 60 per cent. of its life under water; but on pile B, at a point 74 per cent. of the time submerged, and 4 feet above a lower ground-level, no softening was apparent; further, at ground-level of this pile, the percentage being there 87, the softening was no greater than at ground-level at pile A.

It is probable that while the percentage of submersion in moving water hardly appears to affect the result, yet prolonged contact with wet sand, sea-weed, or clinging shell-fish may do so. This seems to suggest that the process of change, as between the sea-water and the iron, is slow, and to be effective must be continuous; so that it is only found to any considerable extent where the water in contact with the surface is still. In the two worst cases, Nos. 1 and 2 of the table, at points 1 foot and 6 inches above ground-level, the surface was in one pile shrouded in a thick mantle of heavy sea-weed, and in the other covered by molluscs; in both instances the surfaces being thus kept moist and undisturbed. The piles of the fourth case were in hard rock, were clean, and, where accessible, always either in moving water or quite dry.

However this may be, the power to resist softening certainly appears to vary largely with the quality of the iron. The piles, referred to above, in which deterioration proceeded at the most rapid rate were certainly of a soft metal, the first being markedly so. On the other hand, certain piles (No. 4) of hard, close-grained iron suffered very little.

It may be mentioned with respect to the last named, as a matter of interest, that the caps of the lower lengths (just above ground-level) had been cast with short pieces of wrought iron projecting—possibly for lifting purposes—which during thirty-eight years had altered in character to something very like softened cast iron, but laminated, and harder. Of about 11/4 inch original thickness, only 3/16 inch remained having the semblance of wrought iron. The percentage of submersion was about 60.

A number of piles, not included in the table, varying from fifteen to forty-four years old, and of the same structure to which set No. 2 belonged, were all found to be hard, with the exception of one showing 3/16 inch of softening. These are omitted, because the mud surrounding them was at the time of examination unusually high, so that the more normal ground-level could not be reached, at which points testing might have disclosed different results. It is probable that for any piles standing in soft material examination below the surface would reveal more pronounced softening than where occasionally exposed.

To meet the effects of sea-water on cast-iron piles, and for other reasons, it is a common and good practice to make the lower lengths of greater thickness—say, 3/8 inch more—than that sufficient for the upper. Occasionally, also, the bottom lengths are filled with concrete, which no doubt adds to the length of time during which they may be relied upon.


                                                                                                                                                                                                                                                                                                           

Clyx.com


Top of Page
Top of Page