Loading the Material for Transportation.—The material excavated by a steam shovel is loaded on cars, wagons or carts. On railway work it is usually loaded on dump or flat cars. On other construction work small dump cars are most generally used, and sometimes wagons or carts. Fig. 66.Fig. 67.Fig. 68. Fig. 69.Fig. 73. Standard gage railway dump cars, Figs. 66 and 67, have nearly gone out of use. They were replaced by the center ridge flat car, Figs. 68 and 69, and it in turn has been replaced by the ordinary flat car. Dump cars are of two styles, dumping either by tipping, Fig. 66, or by means of a hinged sideboard opening on an inclined floor, Fig. 67. Both are heavy, clumsy, costly Fig. 70. Fig. 71. Fig. 72. The brakes are placed on one side of the car, as shown in Figs. 74 and 75. When boulders, loose rock, etc., are to be unloaded, the brake staff is set in a socket, Fig. 76, and taken out before the plow is started. This avoids bending or breaking the staff in case any stone should be wedged between it and the moving plow. Sometimes the socket is used with the brake at its ordinary place at the end of the car; in such a case it must always be taken out before the plow reaches it. The plow, Fig. 70, is built of heavy plate and angle iron, strongly braced, and headed by a cast steel point, to which the Fig. 74. Fig. 75. Fig. 76. The many objections to the center ridge car are almost entirely avoided by the use of the Barnhart plow, Fig. 77, employing the ordinary flat car without any preparations except changing Fig. 77. Fig 78. Fig. 79. On all but very small pieces of work the cars should be provided with hinged drop sideboards, Fig. 79, using either of the arrangements shown in Figs. 80 and 81, which will enable them to carry 12 to 14 cu. yds. instead of 6 or 7. The side boards are made in two pieces on each side of the car, Fig. 79. Those shown in Fig. 80 are used for both center and side plows; they can be quickly dropped by a man walking along the train, after arriving at the unloading place and striking the hook A an upward blow with a light hammer. The boards are hooked up Fig. 80. Fig. 81. The cars should also be provided with sheet iron aprons, Figs. 82 and 83, extending from the end of one car onto the floor of the next, to prevent the material from falling on the track between the cars as the plow is drawn over them, and delaying the departure of the train until it can be shoveled out. These aprons are made either in two pieces, Fig. 82, or in one piece only, Fig. 83. The former are more easily handled, and permit access to the coupling of the cars without lifting the apron. Very little material drops on the track when the aprons and the center plow are used. The single apron is used mostly in connection with the side plow. The number of cars and engines required for each steam shovel to keep it in nearly constant operation depends upon the nature of the material excavated, the length of haul, and the density of other traffic upon the main line. This number must be determined by accompanying circumstances in each case; ordinarily, however, it averages about as given in Table III.: TABLE III.
The length of haul usually ranges from 2 to 15 miles; it seldom exceeds 25 miles for any material except gravel ballast, where hauls of 75 miles are frequent, and sometimes reach 200 miles. Fig. 82. Fig. 83. Fig. 84. Fig 85. On hauls exceeding 25 miles the full number of cars and engines required can seldom be obtained, and the output of the steam shovel is correspondingly decreased. The delay in returning empty cars due to detentions from other trains is the great trouble most keenly felt in steam shovel work on railways in operation. The so-called "mud train" is generally considered an outcast, and is usually the last train to receive the dispatcher's attention for an order to the road. These delays are daily occurrences, and it is quite an exceptional case when the machine is amply supplied with empty cars. The record of most steam shovels on such work is therefore a rather poor one, when the machine really made a good showing for the crippled condition of its car service. Some of these delays can be For general construction work where the excavated material is not loaded on standard gage railway cars, small dump cars, Figs. 84 and 85, are generally used. They are more economical than wagons or carts, which are employed only in special cases, mostly in cities, where the material must be hauled some distance over several intersecting streets, and where a track will not be allowed; or for very small jobs with a long haul which would not justify building a track. The gage of these tracks is usually 2½ or 3 ft., sometimes 2 ft. or even 1½ ft. only; the latter gages are not often used, and the 3-ft. gage is usually preferred. The rails most generally used weigh 20 lbs. per yd. Although these tracks are only temporary their construction should be fairly substantial; but they are often built in an exceedingly careless and insecure manner, causing a great waste of power in pulling the cars over them, and resulting in frequent delays, due to derailments. The grade is usually arranged so that the loaded cars will run downhill by gravity, and only the empty cars need be drawn back to the pit. On small work, horses or mules are used to pull the cars, but on large jobs small locomotives are employed. Small dump cars vary in capacity from 1 to 3 cu. yds., the latter size being most generally used. The side dump car, Fig. 84, dumps on either side. The rotary dump car, Fig. 85, unloads on either side or end; the box can be turned around horizontally, revolving about a vertical pin in a turntable on the frame; they are used mostly in dumping off the end of a fill. In making fills it is nearly always the best plan to build a temporary trestle of round pieces of beech, cottonwood or other cheap trees, old bridge or building timber, or other second-class lumber, and then filling in with the side dump cars. By adopting this plan the unloading will progress much more rapidly than by dumping from the end of a fill, where only one car at a time can be unloaded. These trestles are inexpensive, and the Fig. 86. Fig. 87. Fig. 88. Fig. 89. Unloading the Material.—On railways the unloading is seldom done by slow and expensive hand labor with the shovel; sometimes dump cars are employed, but in most cases flat cars and the plow are used. The trains consist of 10 to 30 cars. The car carrying the plow is attached to the rear of the train at the nearest side track to the unloading place, if it is not over 10 miles from the steam shovel pit this car is generally carried back and forth to avoid an extra stop to couple it on the train at the side track. One end of a steel wire cable is then hooked to the plow and the other end (which is attached to an ordinary car coupling link) coupled to a car or the engine. Usually this cable is about 400 ft. long and extends over 12 cars. The brakes on these cars are then set up tight and the engine started with the forward cars, Fig. 86. In very tenacious or partially frozen material the rear cars are sometimes pulled along by the plow; the wheels are then blocked with pieces of wood or with stones; sometimes it is even necessary to chain a few of these cars to the track to prevent the rear lot of cars from moving. After the plow has been started, it is drawn along slowly until it arrives on the last car, Fig. 87. The engine is then stopped and backed up a few feet to permit the cable to be thrown on one side of the track, Fig. 88. The train is then backed up again and coupled to the unloaded cars, when four to six men throw the cable on the next loaded cars, Fig. 89, coupling its forward end to a car or to the engine if the cable is long enough. The operation is then repeated until all but the car next to the engine is unloaded; this car carries the plow and is Fig. 90. Fig. 91. When filling a trestle the cable cannot be thrown on one side, as described, but must be unhooked from the plow (the rear lot of cars being left standing on the trestle), dragged across the trestle, and there thrown to one side. The forward lot of cars is then backed up until its rear car is opposite the rear end of the cable, when it is loaded, the train backed up, coupled and unloaded, as before described. After unloading the train the cable must again be dragged beyond the trestle, and there thrown to one side of the track and left for the next train. The time required for unloading varies from 10 to 30 minutes, depending upon the nature of the material and the number of cars, and averages about 20 minutes, doing as much work in that time as 20 men can do in a day. When unloading on curves the operations are delayed by the necessity of using snatch blocks on the cars to insure a nearly tangential pull of the cable and avoid pulling the plow off the car. These blocks are applied as shown in Fig. 90, and at A, Fig. 91. They are hooked to long chains extending over the car and fastened to the bolster or arch bar of the truck. The number of snatch blocks required depends upon the degree of the curve and the length of the cable; generally four to six blocks, one to every third car, are enough. As the plow approaches one of these blocks it must be stopped, block and chain removed and transferred forward for use at that end of The steel wire cables used vary from 1 in. to 1½ ins. diameter. The former are used for unloading loose gravel and sandy material; they are light and easily handled, but cannot bear much jerking. The most usual size is 1¼ ins. diameter. Heavier cables require too many men (six to eight) to load them on the car preparatory to starting the plow. One of the heaviest locomotives on the road (preferably one of the consolidation type) should be used for drawing the plow over the cars. These engines are generally able to keep the plow moving with a strong steady pull, avoiding the necessity of taking a run to start the plow, and all injurious jerking of the cable, which frequently breaks it. For tenacious materials and where the haul is not more than 25 miles, it is often good policy to keep one heavy engine at this work, the other engines merely hauling the trains; this can generally be arranged so that no more engines are used than if each engine were to unload its own train. Sometimes two light engines are used for this purpose, but they can seldom move in perfect unison and more or less jerking is the result. Unfortunately the engines for the "mud trains" are not always in the best working order; they are mostly those which are about to go into the shops for turning down the tires or for general repairs, and are not in fit condition for general traffic, but still considered good enough for this service. Expensive delays due to badly working engines are frequently the result. The locomotive in the steam shovel pit should always be equipped with a steam or air driver brake to assist in quickly stopping the cars at exactly the right place when setting them for loading by the steam shovel. For the same reason the brakeman should be allowed to use short sticks in the brake-wheels to obtain a greater leverage in turning them. Both engine and train crews should be changed as little as possible and they should retain their respective trains in the pit on the road or at the dump. Most of the men dislike the "mud train" service, but some (especially the older ones) are glad to get a steady job with a full night's rest, and these are the men Fig. 92. The machine shown in Fig. 92 has lately come into use for pulling the plow over the cars to unload them. This is merely a double cylinder (10 by 12 ins.) reversible hoisting engine, resting on a heavy cast iron bedplate attached to the floor of a box car. Steam is supplied to the engine from the locomotive of the train, which is coupled to this car when the unloading is to begin. With this machine there is no injurious jerking of the cable, and consequently very little breakages or delays, and heavy loads of 15 cu. yds. of tenacious material are readily plowed off the cars in a more satisfactory manner than can be done by any one or two locomotives. Blocking the wheels or chaining cars to the track need not be resorted to; the cars cannot move, for the machine pulls the plow toward itself and the strain is resisted by the cars between them. If it is desired to scatter small quantities of material along the track, as it is often wanted in surfacing or raising track, both plow and train are moved in the same direction at the same or varying speeds, as may be necessary to unload the required amount of material. If a large quantity of material is wanted within a short distance, as usually happens on washouts, train and plow are moved in opposite directions. By moving them in this manner at the same speed, a whole train can be unloaded at any desired spot. Where two locomotives must be used to pull the plow over the cars, the use of this machine will dispense with one of them, and do the work in half the time. On large jobs it should not be missing. The cable is wound around the drum, A, Fig. 92, and must be long enough to extend over the whole length of The steam shovel can be operated continuously throughout the year in all kinds of weather, though operations are often suspended in extremely cold weather. When working in cold weather the face of the bank sometimes freezes during the night to the depth of 3 to 6 ins., but this crust is easily broken in the morning by a few small charges of powder, and then the material can be excavated as easily as at any other season. Fig. 93. Harris & Carter Spreader. Fig. 94. In freezing weather the floors of the cars should be sprinkled with brine just before loading; the brine is kept in barrels at the head of the machine, and one man using an ordinary garden sprinkling can is detailed for the work. This prevents the material from freezing to the floor of the car for three to four hours, and allows it to slip off readily when the plow is put in operation. No train should be left standing over night without unloading. The brine will not prevent freezing for this length of time, and to unload one car of the frozen stuff requires a day's labor of four to six men. Distributing the Material After Unloading.—In widening embankments for side tracks, double track, yard and station grounds, etc., the material is unloaded, as described above, forming a ridge on both sides of the track if unloaded with the center plow, or on one side of the track only if unloaded with the Fig. 95. Edson Spreader. Fig. 96. In the Harris & Carter spreader, Figs. 93 and 94, the car body is cut away between the trucks to receive the two wings which level or spread the material. One or both wings can be used, and they can be raised and lowered to adjust them to any height of new embankment wanted. They will spread the material for a distance of 3 ft. from the rail. When shipping the spreader over the road the wings are drawn up by a hand windlass, revolving about hinges fixed to the braces under the floor of the car, as shown in Fig. 94. In this position the clearance is the same as that of an ordinary passenger car. The Edson spreader, Figs. 95 and 96, has only one wing, attached to an ordinary flat car, and arranged to raise and lower to adjust it to any height of new embankment wanted. The wheel, A, bears against the head of the rail, forming a brace where one is most needed, and greatly assists in preventing a derailment when hard or tenacious materials are suddenly encountered. The cars of both styles of spreaders are loaded with old rails, frogs, scrap iron, etc., to hold them down and prevent derailments when hard or tenacious materials are suddenly encountered. Loads of five to ten tons are generally sufficient, though loads up to 15 tons are sometimes required. Spreaders are usually drawn at a speed of six to eight miles per hour; in loose gravel the speed often reaches 10 miles per hour. They will level off a ridge a mile in length in six to ten minutes, doing as much work in that time as 100 men can do in a day. The spreader is usually stationed in the nearest side track to the unloading place. Frequently it can be hauled between this track and the dump without raising it, or raising it only partially to clear depot platforms, switch stands and other obstructions and thereby avoid the necessity of folding it down on the car while passing between these points. Ordinarily the spreading is done by the last train before the close of the day. In cold weather or on short dumps it must |